Vysočanská, emergency road repairs from Na Jetelce to Nad Krocínkou in Prague 9

The project resolves emergency repairs to ul. Vysočanská in the section from Na Jetelce to Nad Krocínkou.

Construction period: 2017/07 - 2017/12
Total value of the contract: 20 168 084 CZK excluding VAT

A sewer failure resulted in a roadway collapse in July 2016. Vysočanská ulice had been closed since the failure occurred. Surveying work was ordered and then repairs to the sewer collector began. Temporary repairs to the southern part of the road took place at the same time to make the road partially passable for public transport buses.

The project is divided into two construction objects:

SO 101 Vysočanská – road repairs, section from Na Jetelce to Nad Krocínkou

- this object resolves the complete repair of Vysočanská ul. road surfacing, including walkways and reinforced bus lane paving.

SO 102 Vysočanská – subsoil remediation, section from Na Jetelce to Nad Krocínkou

- this object resolves remediation of the road subsoil and the design of variant solutions for the remediation of subsoil using available surveying and diagnostic techniques. The result of the remediation work is a sufficiently stable base for the construction work in SO 101.

The project is begin constructed by Čermák and Hrachovec a.s. COLAS CZ is completing construction of the structural layers and the asphalt road surface.

 

COLAS News

Aug 31

Aquisition of the Finnish company Destia

Colas signs an agreement to acquire Destia, a major player in the road and rail markets in Finland

Aug 31

2021 Half-Year Results of the group Colas

The Board of Directors of Colas, chaired by Frédéric Gardès, met on August 24, 2021 to approve the financial statements at June 30, 2021 and outlook for the current year.

Aug 9

Paris Olympic Games 2024: Colas wins a contract for logistic flow management

Mobility by Colas, the Colas Group’s digital mobility services integrator and operator, has signed a framework contract with the Olympic Structure Delivery Company (SOLIDEO) to design, roll out and operate "last mile" logistic flows for a minimum of 15 months, using the Qievo solution.

Aug 5

BMW PROVING GROUND

The construction season is in full swing, and we were very happy to welcome the top management of BMW to the construction site of the proving ground located near Sokolov.

Jun 30

COLAS CZ among the 3 TOP CONSTRUCTION COMPANIES in 2020!

Tomáš Krones, CEO of COLAS CZ, has received an award for the third place in the competition 2020 TOP CONSTRUCTION COMPANIES, which was presented by Minister of Transport Karel Havlíček.

Jun 8

COLAS is committed to reducing its carbon footprint

In response to the challenges posed by climate change, Colas has made a strong strategic commitment to decarbonizing its business activities. The Group has set itself an ambitious target, in line with the Paris Agreement: reducing its direct greenhouse gas emissions by 30% (scopes 1 and 2) and its indirect upstream emissions by 30% (scope 3a).

Navigation

© 2021 COLAS CZ, a.s. All rights reserved