Structural modifications of internal blocks between Lexova, Josefa Ressla and Jiránkova streets
The total area of the site was c. 30,000 m2.
Construction period: | 2014/10 - 2015/08 |
---|---|
Total value of the contract: | 10 800 000 CZK excluding VAT |
Revitalization of internal blocks, including new storm sewers in a length of 500 m, new public lighting in a length of 1,000 m2, two children's playgrounds, including playground equipment, parking areas and pavements covering an area of approximately 8,000 m2.
Repair of the sewerage system using a trenchless method in a length of 140 m (insertion of a sleeve saturated with resin using hydrostatic pressure of water, followed by slow cooling of the water overnight).