Staré Bohnice 1st stage Bohnická – Ústavní – K Farkám and their vicinity, project No. 999229/1, Praha 8

Within the first stage, the roads will be reconstructed in Bohnická, Ústavní, Nové Butovice, Na Bendovce, U Pazderek, K Farkám streets and the connection between the streets K Farkám and Bohnická in Praha 8 will be executed.

Construction period: 2017/10 - 2019/02
Total value of the contract: 41 823 059 CZK excluding VAT

The roadway is designed with bituminous cover, increased area intersection will be cobbled, pavements then from concrete pavement and part of sidewalks at the monumental building will be made from stone cobbles. Within the contract, new sewerage system, which will be used for drainage of roads, will be set up.Drainage will be adjusted, new traffic signs and greening will be implemented.

Current state of construction: Work on rainwater sewerage is currently under way. The work is carried out by a member of the consortium: Čermák and Hrachovec.

COLAS News

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract for the construction of 13 kilometers of a motorway worth CZK 3,084 BN, which will be realized by COLAS CZ, a.s. in association with FIRESTA-Fišer, rekonstrukce, stavby a.s.

Dec 16

D48 Rybí – Flyover Rychaltice motorway - opening to traffic

On December 15th, 2020, Directorate of roads and motorways opens to traffic the new motorway section D48 Rybí – Flyover Rychaltice.

Nov 2

Merger of Silnice Horšovský Týn a.s.

General Meeting of shareholders decided on the merger by merging the company COLAS CZ, a.s. (= successor business corporation) and the company Silnice Horšovský Týn a.s. (= defunct business corporations).

Oct 30

II/353 Velký Beranov - bypass opens to traffic

The most expensive road construction in the history of the Vysočina Region opens to traffic on the dot exactly according to the schedule set up last spring.