Retaining wall Mincovní St., location 28, 2nd stage

The project concerned static safeguarding of Mincovní Street using an anchored micropile wall. The total secured length of the slope is 113 m.

Construction period: 2015/11 - 2015/12
Total value of the contract: 9 508 488 CZK excluding VAT

The retaining wall was built using 6.7 - 7 m deep piles, 180 mm in diameter. The axial distance is 1.2 m. The borehole heads are terminated in a reinforced concrete strap anchor 500 mm thick, 900 mm high and 100 mm above the level of the existing road. Wood-steel crash barriers are installed along the wall. The existing retaining stone wall at the staircase in the northern part of the section was stabilized by the application of shotcrete C 25/30 with rebar reinforcement 100 x 100 anchored in the base. The executed works will increase the safety of the location, thus improving the standard of living in this part of Jáchymov.

COLAS News

Jun 30

COLAS CZ among the 3 TOP CONSTRUCTION COMPANIES in 2020!

Tomáš Krones, CEO of COLAS CZ, has received an award for the third place in the competition 2020 TOP CONSTRUCTION COMPANIES, which was presented by Minister of Transport Karel Havlíček.

Jun 8

COLAS is committed to reducing its carbon footprint

In response to the challenges posed by climate change, Colas has made a strong strategic commitment to decarbonizing its business activities. The Group has set itself an ambitious target, in line with the Paris Agreement: reducing its direct greenhouse gas emissions by 30% (scopes 1 and 2) and its indirect upstream emissions by 30% (scope 3a).

May 3

COLAS CZ is reconstructing the road route from Vsetín to Rožnov through Valašská Bystřice

On May 3, an extensive reconstruction worth more than CZK 180 million was initiated between Velká Lhota and Valašská Bystřice.

Apr 22

Safety campaign "This is not a war. We all have to survive"

In connection with the spring construction season and loosened travelling within the Czech Republic, we will be happy to recall the campaign "We are not at war, we must survive" and again appealed to drivers to be considerate of our colleagues at sites as well as of the maintenance workers.

Apr 8

8/4/2021 - Environment Day of COLAS Group

The intention is to increase employees' awareness of climate change and its causes.

Apr 7

COLAS CZ realizes construction of a new bridge over Chlumecká Street in Prague 9

A new bridge over Chlumecká Street will be constructed on the Prague D0 ring road worth CZK 170 million.

Navigation

© 2021 COLAS CZ, a.s. All rights reserved