Repair of taxiway TWY A in the section from TWY B to TWY A1

This project involved the reconstruction of holding point THR24 and taxiway TWY A by replacing the surfacing and reinstalling the illuminated beacon lights adhered into penetrations into the new tarmac material.

Construction period: 2016/04 - 2016/04
Total value of the contract: 8 279 183 CZK excluding VAT

Existing taxiway TWY A showed a range of deficiencies, including cracks, surface corrosion and ruts.

In the scope of the load-bearing airport tarmac surfaces defined above, the wear layer was replaced with a new ACO16 S layer using modified asphalt. The new wear layer was 60 mm thick.

The 60 mm thick underlayment was also replaced in 11 m-wide strips symmetrically along the axis of TWY A.

A new ACL 22S layer using modified asphalt was proposed to prevent the formation of rules from slow moving aircraft as they taxi.

The cracks in the underlayment and upper base layers were milled and repaired using fibreglass geo-grids.

Traffic signals and symbols were then applied on the finished asphalt surface to complete the project.

COLAS News

May 3

COLAS CZ is reconstructing the road route from Vsetín to Rožnov through Valašská Bystřice

On May 3, an extensive reconstruction worth more than CZK 180 million was initiated between Velká Lhota and Valašská Bystřice.

Apr 22

Safety campaign "This is not a war. We all have to survive"

In connection with the spring construction season and loosened travelling within the Czech Republic, we will be happy to recall the campaign "We are not at war, we must survive" and again appealed to drivers to be considerate of our colleagues at sites as well as of the maintenance workers.

Apr 8

8/4/2021 - Environment Day of COLAS Group

The intention is to increase employees' awareness of climate change and its causes.

Apr 7

COLAS CZ realizes construction of a new bridge over Chlumecká Street in Prague 9

A new bridge over Chlumecká Street will be constructed on the Prague D0 ring road worth CZK 170 million.

Apr 1

Change of COLAS CZ, a.s. BOD members

With effect from 1 April 2021, the statutory body of COLAS CZ, a.s. is the following company BOD.

Feb 26

COVID-19 - we respond to the current development of the pandemic

We care about the health of our employees and try to do our best to protect them as much as possible at this time!

Navigation

© 2021 COLAS CZ, a.s. All rights reserved