Repair of AB roadway of D1 highway, km 59.105 - 62.043 on the right
Restoration of the road surface, including recycling of the cement stabilisation
Construction period: | 2009/10 - 2009/11 |
---|---|
Total value of the contract: | 51 903 955 |
The work included the repair of crash barriers, the restoration of the bridge ledge, traffic engineering, horizontal marking, new elastic ends on two bridges.