On 1/11/2019, a ceremonial opening to traffic of the project "Reconstruction of the Plumlovská street" in Prostějov was held.

Construction period: 2018/11 - 2019/10
Total value of the contract: 60 122 000 excluding VAT
Contractor:COLAS CZ, a.s. as a general supplier
Project length:1,25 km – urban areas
Number of construction units:8

Construction parameters

Executed area:

asphalt pavements - 10,600 m2

cobbled areas - 9,240 m2

COLAS News

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract with the consortium of companies Colas CZ and FIRESTA-Fišer, rekonstrukce, stavby, which will construct the 13 km long highway section for CZK 3,084 BN.

Dec 16

D48 Rybí – Flyover Rychaltice motorway - opening to traffic

On December 15th, 2020, Directorate of roads and motorways opens to traffic the new motorway section D48 Rybí – Flyover Rychaltice.

Nov 2

Merger of Silnice Horšovský Týn a.s.

General Meeting of shareholders decided on the merger by merging the company COLAS CZ, a.s. (= successor business corporation) and the company Silnice Horšovský Týn a.s. (= defunct business corporations).

Oct 30

II/353 Velký Beranov - bypass opens to traffic

The most expensive road construction in the history of the Vysočina Region opens to traffic on the dot exactly according to the schedule set up last spring.

Navigation

© 2021 COLAS CZ, a.s. All rights reserved