Reconstruction of Smetanova Street in Žďár nad Sázavou
Complete reconstruction of the roadway in Smetanova street in the city of Žďár nad Sázavou.
Construction period: | 2016/05 - 2016/08 |
---|---|
Total value of the contract: | 12 684 152 CZK excluding VAT |
The subject of work was the complete reconstruction of the roadway in Smetanova street incl. connection of local streets Hutařova, Tyršova and road I/37 at intersections and Palachova street to the level of the florist's shop, in a total area of 3,110 m2, the reconstruction of adjacent pavements in Smetanova, Palachova and Brněnská streets with a total surface of 2,028 m2, the reconstruction of 20 street inlets, incl. relevant connections and the reconstruction of public lighting. The construction also includes the replacement planting of 9 trees and the planting of grass on adjacent unpaved surfaces.