III/27513 Jemníky - Bojetice, reconstruction, stage II, km 4.045 - 6.778

The subject of the contract is execution and completion of the construction work on the whole section of the traffic station of this road.

Construction period: 2018/07 - 2018/08
Total value of the contract: 24 160 023 CZK excluding VAT
The construction of the stretch in the above-mentioned range includes complete construction of the road layers, incl. subsoil adjustments. It also includes replacement of the pavement frames affected by the construction, restoration of the horizontal marking and the width adjustment of the road at the site of the existing pedestrian crossings. At the end of the modification, the existing roadway will be expanded within the road body. Outside the built-up part, the cold-recycling of the road will be carried out with the modification of longitudinal and transverse inclines (elevation of the level). Clearing of existing culverts also forms part of the project. Culverts in poor technical condition will be replaced by new pipe culverts with sloping prefabricated ditches.
 
 
 
 

COLAS News

Apr 8

8/4/2021 - Environment Day of COLAS Group

The intention is to increase employees' awareness of climate change and its causes.

Apr 7

COLAS CZ realizes construction of a new bridge over Chlumecká Street in Prague 9

A new bridge over Chlumecká Street will be constructed on the Prague D0 ring road worth CZK 170 million.

Apr 1

Change of COLAS CZ, a.s. BOD members

With effect from 1 April 2021, the statutory body of COLAS CZ, a.s. is the following company BOD.

Feb 26

COVID-19 - we respond to the current development of the pandemic

We care about the health of our employees and try to do our best to protect them as much as possible at this time!

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract for the construction of 13 kilometers of a motorway worth CZK 3,084 BN, which will be realized by COLAS CZ, a.s. in association with FIRESTA-Fišer, rekonstrukce, stavby a.s.