II/193 Domažlice - Havlovice - X I/26

The project concerned reconstruction of road II/193 from the end of Domažlice to the beginning of Havlovice in a length of 1,377 m and from the end of Havlovice to the junction with road I/26 in the direction to Folmava in a length of 677 m.

Construction period: 2015/07 - 2015/08
Total value of the contract: 12 298 565 CZK bez DHP

The total area of the repaired asphalt courses in the road structure was 14,907 m2. 

The roadway was milled in the whole section to the depth of 110 mm and non-supportive spots were repaired. A new ACL 22+ base course was then laid in a thickness of 80 mm and a ACO 11 S wearing course was laid in a thickness of 40 mm. The construction involved reinforcement of the shoulders, the cleaning of ditches and the application of new horizontal marking in the whole length.

COLAS News

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract for the construction of 13 kilometers of a motorway worth CZK 3,084 BN, which will be realized by COLAS CZ, a.s. in association with FIRESTA-Fišer, rekonstrukce, stavby a.s.

Dec 16

D48 Rybí – Flyover Rychaltice motorway - opening to traffic

On December 15th, 2020, Directorate of roads and motorways opens to traffic the new motorway section D48 Rybí – Flyover Rychaltice.

Nov 2

Merger of Silnice Horšovský Týn a.s.

General Meeting of shareholders decided on the merger by merging the company COLAS CZ, a.s. (= successor business corporation) and the company Silnice Horšovský Týn a.s. (= defunct business corporations).

Oct 30

II/353 Velký Beranov - bypass opens to traffic

The most expensive road construction in the history of the Vysočina Region opens to traffic on the dot exactly according to the schedule set up last spring.