I/38 Želetava - border of the region
Reconstruction of 13.5 km long 1st class roadway in the section between the villages Želetava - Zvěrkovice.
Construction period: | 2018/05 - 2019/10 |
---|---|
Total value of the contract: | 173 300224 CZK excluding VAT |
Two types of repairs are proposed:
- replacement of wearing course and binder course with local remediation of unsustainable places (approx. 12 km)
- replacement of the entire asphalt formation including the rehabilitation of the active zone (about 1.5 km)
Further changes and refurbishment of steel barriers, new traffic signs, repairing of culverts, cleaning of roadway shoulders and ditches will be carried out on the whole site.
The project is performed as a consortium of companies: COLAS CZ (the leading member of the consortium), a.s. and EUROVIA CS, a.s. (50% - 50%).