D1 Renovation of carriageway km 199.3 – 204.6 on the left
Renovation of the carriageway asphalt layer encompassed an overall area of 71,419 m2.
Construction period: | 2015/08 - 2015/11 |
---|---|
Total value of the contract: | 143 042 737 CZK excluding VAT |
The investor of the project is the Road and Motorway Directorate of the CR.
The construction project was implemented by the “D1 CM Consortium” consisting of COLAS CZ, a.s. and M-SILNICE a.s. (50%/50%). The leading member of the consortium was COLAS CZ, a.s..
The subject of the project was the repair of a cement concrete carriageway on the D1 motorway consisting in the removal of the existing cement concrete surface in a thickness of 280 mm, application of a new asphalt concrete carriageway 10.75 m wide, and replacement of the asphalt concrete carriageway in a thickness of 120 mm. The construction project included renovation of the carriageway on three bridge structures, including repairs of expansion joints, cleaning of chutes, and repairs of safety equipment on the bridges.