The project concerned continuous maintenance of Ústecká St. in Spořická – Prague boundary in the direction from and to Prague.
Construction period: | 2014/09 - 2014/10 |
---|---|
Total value of the contract: | 16 671 924 CZK excluding VAT |
The construction involved the repair of the roadway using the hot REMIX+ method, stripping of pavement in the existing bus bay and its re-installation in a new formation line, demolition and laying of new kerbstone in the central reserve, modifications of greenery, restoration of crash barriers and traffic signs.