Balabenka – ramps, Project No. 13423, Praha 9
Continuous maintenance of communication in the section of the Balabenka ramp.
Construction period: | 2017/10 - 2018/05 |
---|---|
Total value of the contract: | 15 239 956 CZK excluding VAT |
The pavement milling in a thickness of 110 mm will be performed, followed by asphalt replacement in a thickness of 110 mm. The rectification of surface signs, the repair of the rims and the restoration of traffic signs will be carried out.
Current state of construction: In 2017, 3 stages out of the total number of 5 were realized. The remaining 2 stages will be executed in 2018.