Shortening of traffic restriction on the D1 between Brno and Vyškov, km 199 - 205

November 10, 2015

COLAS CZ, a.s., as the contractor for the D1 roadway reconstruction in km 199.3 - 204.5, managed to shorten the traffic restriction in this section of the highway.

The Road and Highway Directorate will open EXIT 203 Brno – východ for traffic two days before the deadline. Provisional operation will start on 12 November at 6 p.m. Originally, operation was to start on Saturday, 14 November.

"We are aware of the major traffic complications in the Brno area, which are caused mainly by the closure of one lane on the D1 highway in km 199 - 205. However, closure of the whole lane is unavoidable during the application of a new wearing course. We highly appreciate the patience of drivers, whom we always try to help. Based on negotiations with the contractor, we managed to shorten the traffic restriction by two days", said Jan Kroupa, general director of the Road and Highway Directorate.

The shortening of the traffic restriction is possible thanks to COLAS CZ, which made this step beyond the framework of the project and the signed contract.

(source: www.rsd.cz)

COLAS News

Sep 15

Modernization of the II//208 roadway Hlinky - Bochov

On September 9, 2020, the ceremonial handover of this project and its opening to traffic was held.

Aug 17

COLAS CZ partner of the hike on the Javořice hill

Within the project "Up to the Mountain" (Nahoru na horu), we became a partner again - this year of a hike to the Javořice hill.

Jun 18

Ceremonial opening of the workshop in Jihlava

On June 16th, 2020, the workshop in Jihlava was ceremoniously opened as part of the COLAS Group top management visit.

Jun 16

COLAS is building the road infrastructure for the future mobility development center in the Czech Republic

Colas CZ is currently building the road infrastructure for the Future Mobility Development Center in the western Czech city of Sokolov for the BMW group, as part of a joint venture with Colas Projects.

Jun 15

The most successful construction of road management in the Pardubice region

Reconstruction of the III/322 25 road Černá u Bohdanče I. stage, was nominated in The most successful projects competition. The project was carried out by the Pardubice region under the leadership of J. Neradílek (regional manager), together with Bauser CZ, a.s.

May 11

Change of company headquarters

As of 11 May 2020, a decision was taken by the Board of Directors to change the registered office of COLAS CZ. We look forward to seeing you at the company's new headquarters at Rubeška 215/1, 190 00 Prague 9 - Vysočany.

Navigation

© 2020 COLAS CZ, a.s. All rights reserved