Our company participates in the construction of Velký Beranov bypass (Vysočina Region)

June 6, 2019

COLAS CZ is a member of a "Velký Beranov ECS + COLAS Company" consortium of companies with a 50% share.

Performance period:  1.3.2019 to 30.6.2021; 31.10.2020 opening to traffic

Contracted price:  CZK 618 M. The COLAS CZ share is CZK 313,121,073 excl. VAT

Project length: 4.2 km (COLAS section 1.4 km)

Pavement area: approx. 45,000 m2 (out of which 22,000 m2 for COLAS)

Number of construction units: 54

The COLAS CZ section is located in a geomorphologically very rugged area, with bridges alternating with deep cuttings, the deepest of which has a wall height of 16 meters. There are three bridge structures, incl. a four-pole 150-metre long one.

COLAS News

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract with the consortium of companies Colas CZ and FIRESTA-Fišer, rekonstrukce, stavby, which will construct the 13 km long highway section for CZK 3,084 BN.

Dec 16

D48 Rybí – Flyover Rychaltice motorway - opening to traffic

On December 15th, 2020, Directorate of roads and motorways opens to traffic the new motorway section D48 Rybí – Flyover Rychaltice.

Nov 2

Merger of Silnice Horšovský Týn a.s.

General Meeting of shareholders decided on the merger by merging the company COLAS CZ, a.s. (= successor business corporation) and the company Silnice Horšovský Týn a.s. (= defunct business corporations).

Oct 30

II/353 Velký Beranov - bypass opens to traffic

The most expensive road construction in the history of the Vysočina Region opens to traffic on the dot exactly according to the schedule set up last spring.