General Patton´s Bridge in Plzeň opens to traffic

November 8, 2018

On Wednesday November 7th, 2018 the General Patton´s Bridge in Plzeň was opened to traffic. The bridge forms part of the main arterial road in the town centre.

The project involved the bridge reconstruction including the I/20 road as well as the tram track over the river Mže and Tyršova and Lochotínská street.

The current I/20 through road in the section between Rokycanská and Na Roudné streets runs through Tyršova, Jízdecká, Přemyslova streets, the General Patten´s bridge and Karlovarská street. This is the most heavily trafficked town roadway where public transport meets the transit one, incl. the heavy load traffic. The situation is further complicated by the tram and public transport (buses and trolleybuses) traffic as well as by the fact that two 1st class roads converge there - I/20 and I/26 in Tyršova street, I/20 and I/27 in Karlovarská street and three 1st class roads in Přemyslova street).

A rather complicated preparation preceded the bridge reconstruction itself. As there was neither a record of project documentation nor any other document from the 1970´s (the time when the bridge had been constructed) available, a very exacting diagnostics, incl. the loading tests, preceded the project preparation. After that, the load-carrying capacity of the bridge structure was recalculated. During the reconstruction, all these assumptions proved to be accurate and appropriate to the real state of the bridge. Newly used calotte bearings are used on the bridge.

 

I/20 Plzeň, General Patton´s Bridge

Main route:

Length: 226,6 m

Category: MST 20/60

Carriageway area: 4842 m2

Number of bridge units: 3

 

Contractor: Consortium of companies COLAS CZ a Colas Rail

Project price based on the contract: 138 M CZK excl. VAT

Construction period: 05/2017 –  11/2018

COLAS News

Aug 31

Aquisition of the Finnish company Destia

Colas signs an agreement to acquire Destia, a major player in the road and rail markets in Finland

Aug 31

2021 Half-Year Results of the group Colas

The Board of Directors of Colas, chaired by Frédéric Gardès, met on August 24, 2021 to approve the financial statements at June 30, 2021 and outlook for the current year.

Aug 9

Paris Olympic Games 2024: Colas wins a contract for logistic flow management

Mobility by Colas, the Colas Group’s digital mobility services integrator and operator, has signed a framework contract with the Olympic Structure Delivery Company (SOLIDEO) to design, roll out and operate "last mile" logistic flows for a minimum of 15 months, using the Qievo solution.

Aug 5

BMW PROVING GROUND

The construction season is in full swing, and we were very happy to welcome the top management of BMW to the construction site of the proving ground located near Sokolov.

Jun 30

COLAS CZ among the 3 TOP CONSTRUCTION COMPANIES in 2020!

Tomáš Krones, CEO of COLAS CZ, has received an award for the third place in the competition 2020 TOP CONSTRUCTION COMPANIES, which was presented by Minister of Transport Karel Havlíček.

Jun 8

COLAS is committed to reducing its carbon footprint

In response to the challenges posed by climate change, Colas has made a strong strategic commitment to decarbonizing its business activities. The Group has set itself an ambitious target, in line with the Paris Agreement: reducing its direct greenhouse gas emissions by 30% (scopes 1 and 2) and its indirect upstream emissions by 30% (scope 3a).

Navigation

© 2021 COLAS CZ, a.s. All rights reserved