D1 Modernization – section 09, installation of beams

December 16, 2013

Installation of four beams on a SO 09-223 bridge in a length of 34 meters and weighing 80 tonnes.

During the night of 28-29 September 2013, four beams were installed on the SO 09-223 bridge, km 71.435, each with a length of 34 meters and a weight of 80 tonnes.

The work proceeded under the complete closure of the highway at 1.5 hour intervals. The beams were installed according to the timetable and the highway was opened to traffic one hour earlier than planned.

COLAS News

Apr 8

8/4/2021 - Environment Day of COLAS Group

The intention is to increase employees' awareness of climate change and its causes.

Apr 7

COLAS CZ realizes construction of a new bridge over Chlumecká Street in Prague 9

A new bridge over Chlumecká Street will be constructed on the Prague D0 ring road worth CZK 170 million.

Apr 1

Change of COLAS CZ, a.s. BOD members

With effect from 1 April 2021, the statutory body of COLAS CZ, a.s. is the following company BOD.

Feb 26

COVID-19 - we respond to the current development of the pandemic

We care about the health of our employees and try to do our best to protect them as much as possible at this time!

Jan 8

Construction of Southern Tangential tangential trunk road near České Budějovice municipality

Southern tangential trunk road will be performed by consortium of companies COLAS CZ a Firesta-Fišer.

Dec 27

COLAS CZ realizes D48 Bělotín - Nový Jičín project

ŘSD concluded a contract for the construction of 13 kilometers of a motorway worth CZK 3,084 BN, which will be realized by COLAS CZ, a.s. in association with FIRESTA-Fišer, rekonstrukce, stavby a.s.

Navigation

© 2021 COLAS CZ, a.s. All rights reserved