D1 Modernization - Removal of a bridge on km 107

July 2, 2013

The next phase of the construction was the closure of the right lane 7-12 June 2013, which also included the complete closure of the D1 highway for the first time in its history.

The closure was scheduled for 12 hours. During the whole closure, which proceeded from 8 p.m. on 8 June 2013 until 9:20 a.m. on 9 June, object SO 221 was demolished. The flyover was a segmented pre-stressed bridge with monolithic ledges. The demolition was carried out using hydraulic hammers and a mechanism with hydraulic scissors. Cutting of the support structure in half at about 1 a.m. caused the gradual slide of the structure into a prepared gravel bed, which served as protection of the concrete surface of the road. The bridge was then cut into pieces, concrete parts from the left lane were transported and debris from the road surface were removed. After implementation of the safety devices, traffic in the first half of the highway was restored in line with the continuing traffic measures. Work on the demolition of the bridge continued with the other half of the bridge, under the continued closure of the right lane. Everything was achieved without great complications and traffic was restored with a small delay at 9:20 a.m.

COLAS News

Sep 15

Modernization of the II//208 roadway Hlinky - Bochov

On September 9, 2020, the ceremonial handover of this project and its opening to traffic was held.

Aug 17

COLAS CZ partner of the hike on the Javořice hill

Within the project "Up to the Mountain" (Nahoru na horu), we became a partner again - this year of a hike to the Javořice hill.

Jun 18

Ceremonial opening of the workshop in Jihlava

On June 16th, 2020, the workshop in Jihlava was ceremoniously opened as part of the COLAS Group top management visit.

Jun 16

COLAS is building the road infrastructure for the future mobility development center in the Czech Republic

Colas CZ is currently building the road infrastructure for the Future Mobility Development Center in the western Czech city of Sokolov for the BMW group, as part of a joint venture with Colas Projects.

Jun 15

The most successful construction of road management in the Pardubice region

Reconstruction of the III/322 25 road Černá u Bohdanče I. stage, was nominated in The most successful projects competition. The project was carried out by the Pardubice region under the leadership of J. Neradílek (regional manager), together with Bauser CZ, a.s.

May 11

Change of company headquarters

As of 11 May 2020, a decision was taken by the Board of Directors to change the registered office of COLAS CZ. We look forward to seeing you at the company's new headquarters at Rubeška 215/1, 190 00 Prague 9 - Vysočany.

Navigation

© 2020 COLAS CZ, a.s. All rights reserved