Ceremonial tapping of the foundation stone of the "Silnice I/34 Božejov-Ondřejov-Pelhřimov“ project

April 16, 2015

On Thursday, 16 April, the Road and Motorway Directorate started construction of a bypass of route I/34 Božejov – Ondřejov – Pelhřimov, which was attended by Jan Kroupa, general director of the Road and Motorway Directorate

Data on the construction
The main route: 
length: 5,397 m
category: S 11,5/70
the roadway area: 60,500 m2

contractor: Consortium of Božejov - Swietelsky + Strabag + COLAS CZ - leader: SWIETELSKY stavební s.r.o.
price: CZK 448.138 million, excl. VAT
length of construction: 31 months

"Construction of this road relocation will result in the significant mitigation of negative effects on the population in the affected municipalities. The technical concept also eliminates to the greatest possible extent all impacts on the environment", said Jan Kroupa, general director of the Road and Motorway Directorate. 

The start of the route is at km 82.300, where this route follows up the "Nová Ves – Božejov" construction, and the end is located at km 87.697. The western bypass of Pelhřimov is planned in future years.

The construction has been proposed for inclusion in the Operational Programme Doprava 2014-2020 and will be co-financed by the European Regional Development Fund.

COLAS News

Aug 31

Aquisition of the Finnish company Destia

Colas signs an agreement to acquire Destia, a major player in the road and rail markets in Finland

Aug 31

2021 Half-Year Results of the group Colas

The Board of Directors of Colas, chaired by Frédéric Gardès, met on August 24, 2021 to approve the financial statements at June 30, 2021 and outlook for the current year.

Aug 9

Paris Olympic Games 2024: Colas wins a contract for logistic flow management

Mobility by Colas, the Colas Group’s digital mobility services integrator and operator, has signed a framework contract with the Olympic Structure Delivery Company (SOLIDEO) to design, roll out and operate "last mile" logistic flows for a minimum of 15 months, using the Qievo solution.

Aug 5

BMW PROVING GROUND

The construction season is in full swing, and we were very happy to welcome the top management of BMW to the construction site of the proving ground located near Sokolov.

Jun 30

COLAS CZ among the 3 TOP CONSTRUCTION COMPANIES in 2020!

Tomáš Krones, CEO of COLAS CZ, has received an award for the third place in the competition 2020 TOP CONSTRUCTION COMPANIES, which was presented by Minister of Transport Karel Havlíček.

Jun 8

COLAS is committed to reducing its carbon footprint

In response to the challenges posed by climate change, Colas has made a strong strategic commitment to decarbonizing its business activities. The Group has set itself an ambitious target, in line with the Paris Agreement: reducing its direct greenhouse gas emissions by 30% (scopes 1 and 2) and its indirect upstream emissions by 30% (scope 3a).

Navigation

© 2021 COLAS CZ, a.s. All rights reserved