Zenklova – noise elimination, 1st stage, Project No. 999954/1

The subject of the contract is reconstruction of the bridge and that of a part of Zenklova street.

Construction period: 2017/10 - 2018/10
Total value of the contract: 48 810 178 CZK excluding VAT

The project includes  reconstruction of the bridge over Rokytka R004 in Zenklova street. In addition, the roadways in Zenklova street will be replaced on the following roads - Elsnicovo square and Dr. V. Holý square, which will reduce the overall noise burden in the area. Bridge and road construction will be performed in existing parameters.

Current state of work: The project began with the reduction of the tram line in one. Work on engineering networks is underway - probes are being done.

COLAS News

Nov 15

Reconstruction of the Plumlovská street

On 1/11/2019, a ceremonial opening to traffic of the project "Reconstruction of the Plumlovská street" in Prostějov was held.

Aug 28

COLAS CZ becomes a patron of the Secondary School in Nový Bydžov

We became a patron of the Secondary Technical and Craft School in Nový Bydžov.

Aug 16

COLAS CZ on the D10 highway near Mladá Boleslav

We try to reduce the risk of traffic accidents at construction sites executed under traffic.

Jul 15

WATTWAY – a new life for roads

This is a unique project of the COLAS company. In principle, it is a "solar road", where the solar energy is used like in standard photovoltaic panels.

Jul 3

Photo contest "My dad works here!" launched

As part of the security campaign "My Dad Works Here!", in effect till the end of next year, a new Photo Contest has been launched in all countries of the COLAS Europe Group.

Navigation

© 2019 COLAS CZ, a.s. All rights reserved