Sewerage and WTP Jamné

The project involves a new sewage system for the entire Jamné municipality concluded with a new water treatment plant with a capacity of 600EO.

Construction period: 2017/03 - 2018/09
Total value of the contract: 54 696 347 CZK excluding VAT

Currently, a unified sewerage network is operating in the municipality, however, it is not connected to a WTP. After completion of the construction of a new sewerage system, the existing sewage system will be used solely for drainpipe.

Sewerage is designed primarily as a gravitational DN 250 mm in the length of 3,835.2 m. In areas where, due to the depth, it is impossible to use the gravity pipelines, the pressure sewer in the length of 836.3 meters is designed. The sewer pumps waste water of the three sewage pumping wells back into the gravity system. The fourth pumping station is located in front of the new mechanical-biological waste water treatment plant and pumps all the municipality´s sewage into the tanks of the water treatment plant. Treated waste water flows back into the nearby watercourse.

COLAS News

Feb 15

COLAS CZ supports EBEC

We decided to support the technical education of students at the Faculty of Civil Engineering of Brno University of Technology and we have become a guarantor of EBEC competition, where students will prove their knowledge in practice.

Feb 13

COLAS Team Cup - final results

The COLAS Team Cup World Finals were held on 7 and 8 February, 2018, in Paris.

Dec 4

COLAS CZ, a.s. at the JobChallenge Job Fair

This year's job fair for students and graduates took place on 22.11.2017 in Brno and our company could not be missed like every year.

Dec 1

Breakfast with COLAS! - Students of the Secondary School of Civil Engineering in Mělník

On Wednesday, 15th November, we welcomed students to the headquarters of the company in Prague. This time visited us students of the 3rd year from Secondary School of Civil Engineering in Mělník.

© 2018 COLAS CZ, a.s. All rights reserved