Retaining wall Mincovní St., location 28, 2nd stage

The project concerned static safeguarding of Mincovní Street using an anchored micropile wall. The total secured length of the slope is 113 m.

Construction period: 2015/11 - 2015/12
Total value of the contract: 9 508 488 CZK excluding VAT

The retaining wall was built using 6.7 - 7 m deep piles, 180 mm in diameter. The axial distance is 1.2 m. The borehole heads are terminated in a reinforced concrete strap anchor 500 mm thick, 900 mm high and 100 mm above the level of the existing road. Wood-steel crash barriers are installed along the wall. The existing retaining stone wall at the staircase in the northern part of the section was stabilized by the application of shotcrete C 25/30 with rebar reinforcement 100 x 100 anchored in the base. The executed works will increase the safety of the location, thus improving the standard of living in this part of Jáchymov.

COLAS News

Jun 6

Award for COLAS CZ, a.s. in the 2017 TOP Building Company competition

On June, 2018, Tomáš Krones, Chairman od the Board of Directors of COLAS CZ, received an award for the second place in the 2017 TOP Building Company competition.

May 18

Professional internship from Hungary on the bridges

At the instigation of our talents, we provide internships to share experience between us and sister companies abroad.

May 17

Open Day in Bašnice

The Bašnice profit centre held an open day event on 28 April, 2018.

Apr 26

Marathon in Vienna with the participation of athletes from COLAS CZ

On Sunday, April 22, 2018, a marathon was held in Vienna, where four of our colleagues participated.

© 2018 COLAS CZ, a.s. All rights reserved