D5 motorway Rozvadov at km 148.9 - 150.8

This project is located in a rural area nearby the Rozvadov crossing at the Czech/German border.

Construction period: 2016/07 - 2016/09
Total value of the contract: 19 513 334 CZK excluding VAT

Customs and passport control were cancelled at the Rozvadov border crossing with Czech Republic’s entry into the Schengen Area effective 21 December 2007. Trucks and passenger cars were permitted to use the former customs areas off the motorway itself as a rest area.

A total of 1504.6 m2 of pavement will be replaced in the area of the former roof shelters between the former island structures.

The pavement itself will comprise the following elements:

mastic asphalt later modified with polymer PMB 45/80-60 with milling on the SMA 11S surface 40 mm ČSN EN 13108-5
spray applied bonding emulsion with PS-EP modification 0.30 kg/m² ČSN 73 6129
very coarse asphalt concrete modified with polymer PMB 25/55-60 ACL 22S 80 mm ČSN EN 13108-1
spray applied bonding emulsion with PS-EP modification 0.30 kg/m² ČSN 73 6129
coarse grained coated aggregate ACP 22S 60 mm ČSN EN 13108-1
spray applied bonding emulsion with PS-E 0.30 kg/m² ČSN 73 6129
coarse grained coated aggregate ACP 22S 60 mm ČSN EN 13108-1
penetrating spray thinned with asphalt emulsion 1.0 kg/m² ČSN 73 6129
chipseal layer using fraction 0/32 MZKGA aggregates 200 mm ČSN 73 6126-1
crushed gravel, fraction 0/45 ŠDA min. 210 mm ČSN 73 6126-1

The project involves the removal of the existing portal structure installed on the main route at km 149.860 to 150.375. The guardrails require a higher level of support in the central median due to the removal of the existing public lighting lamps (SO 430) and the removal of the unused traffic sign portal. The project involves the replacement of the existing single-sided guardrail at the H2 level of retention for the entire section. The total length of guardrails in the central median is 3,500 m.

COLAS News

Jun 6

Award for COLAS CZ, a.s. in the 2017 TOP Building Company competition

On June 4th, 2018, Tomáš Krones, Chairman of the Board of Directors of COLAS CZ, received an award for the second place in the 2017 TOP Building Company competition.

May 18

Professional internship from Hungary on the bridges

At the instigation of our talents, we provide internships to share experience between us and sister companies abroad.

May 17

Open Day in Bašnice

The Bašnice profit centre held an open day event on 28 April, 2018.

Apr 26

Marathon in Vienna with the participation of athletes from COLAS CZ

On Sunday, April 22, 2018, a marathon was held in Vienna, where four of our colleagues participated.

© 2018 COLAS CZ, a.s. All rights reserved