D10 median strip modification

In this project, COLAS CZ is installing 19 median strip crossings in lengths of 120 and 135 m.

Construction period: 2016/08 - 2017/06
Total value of the contract: 122 490 000 CZK excluding VAT

The work is being performed by the ‘D10 Median Strip Modification Consortium’ composed of STRABAG a.s. (Leading Member of Consortium) and COLAS CZ, a.s.

The work repeats at individual crossings and involves the removal of the existing structures, i.e. crash barriers, or possible existing short crossings. Due to the fact that fibre-optic cables in HDPE pipes are installed below the median strips, the earthwork is slightly complicated.

The crossings include a new multi-duct cable line, the relaying of CETIN (Czech Telecommunication Infrastructure) technology, drainage, new roadway construction, in some cases drainage with a gravel shoulder, and the installation of new steel crash barriers.

The crossings are divided in closures and are implemented in individual parts of the permitted traffic engineering.

 

COLAS News

Jun 6

Award for COLAS CZ, a.s. in the 2017 TOP Building Company competition

On June 4th, 2018, Tomáš Krones, Chairman of the Board of Directors of COLAS CZ, received an award for the second place in the 2017 TOP Building Company competition.

May 18

Professional internship from Hungary on the bridges

At the instigation of our talents, we provide internships to share experience between us and sister companies abroad.

May 17

Open Day in Bašnice

The Bašnice profit centre held an open day event on 28 April, 2018.

Apr 26

Marathon in Vienna with the participation of athletes from COLAS CZ

On Sunday, April 22, 2018, a marathon was held in Vienna, where four of our colleagues participated.

© 2018 COLAS CZ, a.s. All rights reserved