Bypass Sokolov – Svatava, phase 3

The construction solves the bypass of the city of Sokolov and the municipality of Svatava.

Construction period: 2015/09 - 2016/03
Total value of the contract: 112 981 233 CZK excluding VAT

The construction solves the bypass of the city of Sokolov and the municipality of Svatava. The newly designed disposition will divert transit traffic from inhabited areas and reduce intensive traffic in the immediate centre. The road relocation starts with a passable branch (joining intersection) on road III/210 in front of the bridge structure SO 202 with a connection to the completed part. From the start of the section the route of the relocation leads over the bridge structure, crossing road III/210 29, the Sokolov - Svatava railway line, the Svatava River, and continues in an open line, first on the embankment with a length of 250 m. The road is category S9, 5/50. The minimal directional radius is 150 m, the maximum road ascent within the stage is 2.2%. The road composition is designed according to TP 170 for class III of traffic loading and the design level D0. The surface has a straight line camber of 2.5%, one-sided in bends.

 

Bridge characteristics across III/21029, the railroad and Svatava River:

The work involves the construction of a permanent road bridge with 7 spans and an upper roadway. Composite steel-concrete multispan continuous beam of constant height. Lower structure massive monolithic ferro-concrete pillars, massive ferro-concrete supports with parallel wing walls, deep foundation on piles.

Overbridge length: 295.5 m
Bridge length: 310.4 m
Span: 36 + 45 + 45 +45 + 45 + 45 + 36 m
Bridge height above rail surface: 6.56 m
Bridge height above rail surface: 5.25 m
Building height: 2.615 m
Free bridge width: 12.0 m
Bridge loading: endurance class A according to ČSN 73 6203

COLAS News

Aug 28

COLAS CZ becomes a patron of the Secondary School in Nový Bydžov

We became a patron of the Secondary Technical and Craft School in Nový Bydžov.

Aug 16

COLAS CZ on the D10 highway near Mladá Boleslav

We try to reduce the risk of traffic accidents at construction sites executed under traffic.

Jul 15

WATTWAY – a new life for roads

This is a unique project of the COLAS company. In principle, it is a "solar road", where the solar energy is used like in standard photovoltaic panels.

Jul 3

Photo contest "My dad works here!" launched

As part of the security campaign "My Dad Works Here!", in effect till the end of next year, a new Photo Contest has been launched in all countries of the COLAS Europe Group.

Jul 1

COLAS CZ at the Chateau Garden in Oslavany

COLAS CZ executed the construction of Chateau Garden Oslavany - 2nd and 3rd stage worth CZK M 35.

Navigation

© 2019 COLAS CZ, a.s. All rights reserved