Progress of the first work on the D1 – section 14

July 2, 2013

The first phase of construction involved the implementation of central reserve crossings at the beginning and end to transfer the traffic during the various stages of construction.

At present, the scheduled extension of the left lane is being finished. This stage will be followed by closure of the fast lanes of the highway for work on the central reserve (cable lines, trench and trenchless part of the sewer system).

COLAS News

May 18

Professional internship from Hungary on the bridges

At the instigation of our talents, we provide internships to share experience between us and sister companies abroad.

May 17

Open Day in Bašnice

The Bašnice profit centre held an open day event on 28 April, 2018.

Apr 26

Marathon in Vienna with the participation of athletes from COLAS CZ

On Sunday, April 22, 2018, a marathon was held in Vienna, where four of our colleagues participated.

Apr 13

Second Corporate meeting of COLAS Group in CZ´s staff

The second Corporate meeting of COLAS CZ Group employees took place on March 20 and 21, 2018, at Hotel Harmony in Špindlerův Mlýn.

© 2018 COLAS CZ, a.s. All rights reserved