D1 Modernization – section 14, EXIT 104 Větrný Jeníkov – EXIT 112 Jihlava

July 2, 2013

The tender of the Roads and Motorways Directorate CR for the reconstruction of the D1 highway in section 14 was won by consortium "CPI pro D1" consisting of COLAS CZ, a.s. and Porr a.s. The leading member of this consortium is COLAS CZ, a.s.

The summary of contracts with the contractor (investor) was signed on 10 April 2013. On 12 April, we took over the construction site for preparatory work and the actual implementation began on 9 May at 6 a.m.

Section 14 involves the modernization of the D1 highway in a length of 8.5 km to category D28/120. It includes the construction of 7 bridges, the complete reconstruction of the sewer system, drainage, cable lines and the complete exchange of the concrete roadway. The construction will proceed under limited traffic at partial stages. The traffic will always be maintained on at least one half of the highway.

Opening for traffic is expected in October 2014.

COLAS News

Aug 2

I/34 Božejov-Ondřejov-Pelhřimov bypass opens to traffic

On Tuesday August 1st, 2017, a new section of the I/34 road between Božejov and Pelhřimov was opened to traffic.

Jun 30

COLAS Team Cup - qualification five-a-side soccer

This year, Mr. Hervé Le Bouc, CEO and Chairman of the COLAS Management Board, decided to create a worldwide in-house sports event, called Colas Team Cup. Two sport were chosen - five-a-side soccer and running.

Apr 19

COLAS CZ, a.s. and Čermák and Hrachovec a.s. at the iKariéra 2017 Job Fair in Brno

On April 11, 2017 we attended the job fair iKariéra at the Faculty of Business and Management at the University of Technology in Brno.

Apr 6

COLAS CZ, a.s. and Čermák a Hrachovec a.s. at the iKariéra 2017 Job Fair in Prague

On March 29, 2017 we attended for the third time the job fair iKariéra at the Construction Faculty of the Czech Technical University in Prague.

© 2017 COLAS CZ, a.s. All rights reserved