D1 Modernization – section 09, installation of beams

December 16, 2013

Installation of four beams on a SO 09-223 bridge in a length of 34 meters and weighing 80 tonnes.

During the night of 28-29 September 2013, four beams were installed on the SO 09-223 bridge, km 71.435, each with a length of 34 meters and a weight of 80 tonnes.

The work proceeded under the complete closure of the highway at 1.5 hour intervals. The beams were installed according to the timetable and the highway was opened to traffic one hour earlier than planned.

COLAS News

Apr 13

Second Corporate meeting of COLAS Group in CZ´s staff

The second Corporate meeting of COLAS CZ Group employees took place on March 20 and 21, 2018, at Hotel Harmony in Špindlerův Mlýn.

Feb 15

COLAS CZ supports EBEC

We decided to support the technical education of students at the Faculty of Civil Engineering of Brno University of Technology and we have become a guarantor of EBEC competition, where students will prove their knowledge in practice.

Feb 13

COLAS Team Cup - final results

The COLAS Team Cup World Finals were held on 7 and 8 February, 2018, in Paris.

Dec 4

COLAS CZ, a.s. at the JobChallenge Job Fair

This year's job fair for students and graduates took place on 22.11.2017 in Brno and our company could not be missed like every year.

© 2018 COLAS CZ, a.s. All rights reserved